The PPA Utilization dashboard allows Resource Managers to monitor various aspects of resource and capacity utilization across departments and locations and for a specific month. This dashboard helps Resource Managers to view the utilization of resources and to view trends in project utilization of a resource.
This dashboard helps Resource Managers to answer the following questions:
This dashboard consists of the following sections:
Metric Name | Description | Formula | Expected Values |
---|---|---|---|
Allocation Gap % | Percentage of hours where resources are falling short and unable to meet their allocated hours | (([Resource Allocated Hours] - [Resource Actual Hours]) / [Resource Allocated Hours]) | 0 or >0, closer to 0 is ideal |
Avg Hourly Rate | The average rate of work per hour for the project | [Project Actual Cost] / [Project Actual Effort (Hours)] | 0 or >0 |
Capacity Utilization % | Time spent by resource on project compared to its total capacity | [Resource Actual Hours] / [Capacity Hours] | 0 or >0, closer to 100% is ideal |
Project Utilization % | Percentage of actual hours logged by a resource as compared to their allocated hours | ([Resource Actual Hours] / [Resource Allocated Hours]) | 0 or >0, closer to 100% is ideal |
No. of Resources | Count of all resources across projects | Max [No. of Resources] | 0 or >0 |
Resource Actual Hours | Amount of actual project work logged by the resource using timesheets | Sum (Resource Actual Hours) | 0 or >0, greater than 0 is ideal |
Resource Allocated Hours | Total number of hours allocated by resource manager to projects | Sum (Resource Allocated Hours) | 0 or >0 |
Capacity Hours | Capacity of the resource in hours and is defined at user resource level | Sum (Capacity Hours) | 0 or >0 |