The PPA Resource Alignment dashboard allows Project Managers and Portfolio Managers to view and monitor the allocation and utilization of resources across various projects. It displays the details of the resources who were allocated to the projects and their performance in terms of number of projects worked on and effort variance. It also displays the weekly trends of utilization, overtime, actual effort and effort variance across projects providing a clear picture of how well aligned the allocated resources are with the expectations of the Project Manager.
This dashboard consists of the following sections:
Metric Name | Description | Formula | Expected Values |
---|---|---|---|
No. of Projects | Total number of projects | Count ([No. of Projects]) | 0 or >0 |
Project Allocation % | The percentage of hours that are allocated to projects as compared to the total planned hours | [Resource Allocated Hours] / [Resource Planned Effort (Hours)] | 0 or >0, closer to 100% is ideal |
Project Utilization % | Percentage of actual hours logged by a resource as compared to their allocated hours | ([Resource Actual Hours] / [Resource Allocated Hours]) | 0 or >0, closer to 100% is ideal |
Missed Project Credit | The cost incurred in the event of an allocated resource not working on a project | ([Resource Actual Hours] - [Resource Planned Effort (Hours)]) * [Avg Hourly Rate] | 0, >0, or <0 |
Overtime Hours | The extra hours clocked in by a resource for a project. Number of hours spent by a resource beyond the allocated time is considered to be overtime hours | IF (([Resource Actual Hours] > [Resource Planned Effort (Hours)]) THEN ([Resource Actual Hours] - [Resource Planned Effort (Hours)]) ELSE 0) | 0 or >0, closer to 0 is ideal |
Timecard Non-Compliance % | The percentage of actual time spent by a resource which is less than the allocated hours for projects | 1 - ([Resource Actual Hours] / [Resource Allocated Hours]) | 0 or >0, closer to 0 is ideal |
Resource Actual Hours | Amount of actual project work logged by the resource using timesheets | Sum (Resource Actual Hours) | 0 or >0, greater than 0 is ideal |
Effort Variance | The effort difference between the allocated and actual effort of a resource | ([Resource Allocated Hours] - [Resource Actual Hours]) | 0, <0, or >0 |
Resource Allocated Hours | Total number of hours allocated by resource manager to projects | Sum (Resource Allocated Hours) | 0 or >0 |
Resource Planned Effort (Hours) | The hours planned for a resource for a task or project | Sum [Resource Planned Effort (Hours)] | 0 or >0 |
Resource Planned Effort Cost | The planned cost for a resource for a task or project | Sum [Resource Planned Effort Cost] | 0 or >0 |
Resource Actual Cost | The actual cost of all the resources associated with all the tasks within a project | [Resource Actual Hours] * [Resource Per Hour Cost] | 0 or >0 |