The PPA Project Executive Overview dashboard allows Project Executives and Project Managers to monitor allocation and utilization of resources across various portfolios and resource groups. It also allows them to view a breakdown of resources by employment type, role, department, portfolio, and program.
This dashboard consists of the following sections:
Metric Name | Description | Formula | Expected Values |
---|---|---|---|
No. of Contractors | Total number of contractors who are assigned to projects | Max([No. of Available Resources]) where [Employment Type = CONTRACTOR And Resource Not in (0,-1)] | 0 or >0 |
No. of FTEs | Total number of full time employees who are assigned to projects | Max([No. of Available Resources]) where[Employment Type = FTE And Resource Not in (0,-1)] | 0 or >0 |
No. of Resources | Count of all resources across projects | Max [No. of Resources] | 0 or >0 |
Resource Planned Effort Cost | The planned cost for a resource for a task or project | Sum [Resource Planned Effort Cost] | 0 or >0 |
Project Allocation % | The percentage of hours that are allocated to projects as compared tototal planned hours | [Resource Allocated Hours] / [Resource Planned Effort (Hours)] | 0 or >0, closer to 100% is ideal |
Project Utilization % | Percentage of actual hours logged by a resource as compared to their allocated hours | ([Resource Actual Hours] / [Resource Allocated Hours]) | 0 or >0, closer to 100% is ideal |
Availability Gap % | Percentage of hours where the resource availability is falling short for project demand | ([Resource Planned Effort (Hours)] - [Resource Allocated Hours]) / [Resource Planned Effort (Hours)] | 0 or >0, closer to 0 is ideal |
Avg Hourly Rate | The average rate of work per hour for the project | [Project Actual Cost] / [Project Actual Effort (Hours)] | 0 or >0 |