Project Analysis

The PPA Project Analysis dashboard allows a Project Manager to monitor the performance of the selected projects based on cost, effort and schedule variances on a month-on-month basis. The Project Manager may also view information such as variances in cost, effort and schedule, number of project milestones that were not met, and actual percentage of projects that are completed.

Note: This dashboard is currently not available as the Snapshots feature is in development

This dashboard contains the following sections:

Metrics Used

Metric Name Description Formula Expected Values
EVM_Cost Variance % The percentage difference between actual cost and earned value of the project. Avg([Project Cost Variance %]) 0 % to 100 %
EVM_Schedule Variance % The percentage difference between the Actual and the Planned duration of a project. Avg([Project Schedule Variance %]) 0 % to 100 %
EVM_Effort Variance % The percentage difference between actual and planned efforts of a project. Avg([Project Effort Variance %]) 0 % to 100 %
No. of Milestones Slipped Number of milestone tasks that breached the respective planned end date. Count([No. of Project Tasks]) where [Project Task Is Milestone Slipped= Y] 0 or >0, closer to 0 is ideal
Actual % Complete Percentage of work in the project that has completed Sum ([Project Actual % Complete]) 0 % to 100 %
Schedule Variance % The percentage difference between the Actual and the Planned duration of a project. Avg([Project Schedule Variance %]) 0 % to 100 %
Planned Effort (Hours) The number of hours planned for a resource, for a project. Sum([Project Planned Effort (Hours)]) 0 or >0
Actual Effort (Hours) The actual number of time (in hours) spent by a resource on a project

Sum([Project Actual Effort (Hours)])

0 or >0
Effort Variance (Hours) The effort difference between the actual and the planned effort of a project. ([Project Actual Effort (Hours)] - ([Project Planned Effort (Hours)] * [Project Actual % Complete])) 0 or >0
Resource Planned Effort (Hours) The hours planned for a resource for a task or project Sum [Resource Planned Effort (Hours)] 0 or >0
Resource Actual Hours Amount of actual project work logged by the resource using timesheets Sum (Resource Actual Hours) 0 or >0, greater than 0 is ideal
Overtime Hours The extra hours clocked in by a resource for a project. Number of hours spent by a resource beyond the allocated time is considered to be overtime hours IF (([Resource Actual Hours] > [Resource Planned Effort (Hours)]) THEN ([Resource Actual Hours] - [Resource Planned Effort (Hours)]) ELSE 0) 0 or >0, closer to 0 is ideal