The PPA Portfolio Manager's View dashboard allows a Portfolio Manager to monitor the performance of projects and Project Managers within the selected portfolios. Using this dashboard, you can view the distribution of projects within the portfolio based on their status, monitor the performance of Project Managers based on cost and schedule variances, and monitor various aspects of the projects managed by them such as Sub Project Count, Project Planned Start Date and Actual Start Date, and variances in cost, effort, and schedule. Additionally, for the selected Portfolio Managers, you can also view the Project Success Ratio, percentage of projects that were completed within the planned budget and time, and the distribution of projects based on the risk associated with them.
In summary, this dashboard helps a Portfolio Manager answer the following questions:
Note: This dashboard is currently not available as the Snapshot feature is still in development.
This dashboard consists of the following sections:
Metric Name | Description | Formula | Expected Values |
---|---|---|---|
EVM_Schedule Variance % | The percentage difference between the Actual and the Planned duration of a project. | Avg([Project Schedule Variance %]) | 0 % to 100 % |
Cost Variance (Act vs Planned) | The cost difference between the actual and the planned cost of the project | [Project Actual Cost] - [Project Planned Cost] | 0 or >0 |
Project Success Ratio |
The percentage of projects that are within budget and schedule. | ([No. of Projects Within Budget & Schedule] / [No. of Projects]) | 0 % to 100 % |
Completed In Budget % | Percentage of projects that have completed within their planned budget | ([No. of Projects Closed Within Budget] / [No. of Closed Projects]) | 0 % to 100 % |
Completed In Time % | Percentage of projects that have completed within their planned schedule | ([No. of Projects Closed Within Schedule] / [No. of Closed Projects]) | 0 % to 100 % |
High | Total number of projects where risk is set to High | Count ([No. of Projects]) where [Project Risk = HIGH] | 0 or >0 |
Medium | Total number of projects where risk is set to Medium | Count ([No. of Projects]) where [Project Risk = MEDIUM] | 0 or >0 |
Low | Total number of projects where risk is set to Low | Count ([No. of Projects]) where [Project Risk = LOW] | 0 or >0 |
EVM_Schedule Variance % | The percentage difference between the Actual and the Planned duration of a project. | Avg([Project Schedule Variance %]) | 0 % to 100 % |
EVM_Effort Variance % | The percentage difference between actual and planned efforts of a project. | Avg([Project Effort Variance %]) | 0 %to 100 % |