Allocation

The PPA Allocation dashboard allows a Resource Manager to analyze the allocation of resources across departments and geographical locations.

The Resource Manager can view an overall summary of the allocation of a resource based on two perspectives:

Using these perspectives, a Resource Manager can view the allocation based on the Project Manager's resource requests and resource's capacity. Other key questions that this dashboard answers are:

  1. What percentage of resources are not allocated to any projects? How do different Resource Managers perform with respect to this metric?
  2. What is the net available capacity of resources after removing all the allocated effort?
  3. What is cost associated with allocations?
  4. What is the allocation pattern for different roles?
  5. What is the week-on-week trend of allocated and actual hours for a resource?

This dashboard consists of the following sections:

Metrics Used:

Metric Name Description Formula

Expected Value

Resource Allocation % Percentage of allocation done to a resource as per the resource's capacity [Resource Allocated Hours] / [Capacity Hours] 0 or >0, closer to 100% is ideal
% Resources Not Allocated Percentage of resources who are not allocated to any projects (([No. of Available Resources (Excl. 0,-1)] - [No. of Assigned Resources (Excl. 0,-1))]) / [No. of Available Resources (Excl. 0,-1)]) 0 or >0, closer to 0 is ideal
Project Allocation % The percentage of hours that are allocated to projects as compared to total planned hours [Resource Allocated Hours] / [Resource Planned Effort (Hours)] 0 or >0, closer to 100% is ideal
Net Available Capacity Available capacity of resource after removing all engagements [Capacity Hours] - [Resource Planned Effort (Hours)] 0 or >0, greater than 0 is ideal
Resource Allocated Cost The cost associated to the allocated resource. The resource can be allocated either at the task or project level. Sum (Resource Allocated Cost) 0 or >0
No. of Resources Count of all resources across projects Max [No. of Resources] 0 or >0
Resource Actual Hours Amount of actual project work logged by the resource using timesheets Sum (Resource Actual Hours) 0 or >0, greater than 0 is ideal
Resource Allocated Hours Total number of hours allocated by resource manager to projects Sum (Resource Allocated Hours) 0 or >0
Resource Planned Effort (Hours) The hours planned for a resource for a task or project Sum [Resource Planned Effort (Hours)] 0 or >0
Capacity Hours Capacity of the resource in hours and is defined at resource level Sum (Capacity Hours) 0 or >0